Legislation Details

File #: TMP-11546    Version: 1 Name:
Type: Contract Status: Miscellaneous
File created: 5/5/2026 In control: Community Services Department
On agenda: 5/26/2026 Final action:
Title: Recommendation to approve Construction Change Order No. 05, for the Senior Services Phase 1 Remodel Project - PWP WA 2024-144 between Washoe County and Houston Smith Construction, Incorporated [in the not to exceed amount of $19,891.73, for a total contract amount not to exceed $889,956.35] and extend the project timeline to June 30, 2026.  This request conforms to Nevada Revised Statutes and Washoe County policy requirements for project cost increases exceeding $25,000.00 or 5%, whichever is greater, of the original approved contract amount.  Change Order No. 05 is required due to unforeseen work not identified in the original contract award.  Community Services. (Commission District 3.) FOR POSSIBLE ACTION
Attachments: 1. 5-26-26-StaffReport-SrCenterPhase1ProjectChangeOrder
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Recommendation to approve Construction Change Order No. 05, for the Senior Services Phase 1 Remodel Project - PWP WA 2024-144 between Washoe County and Houston Smith Construction, Incorporated [in the not to exceed amount of $19,891.73, for a total contract amount not to exceed $889,956.35] and extend the project timeline to June 30, 2026.  This request conforms to Nevada Revised Statutes and Washoe County policy requirements for project cost increases exceeding $25,000.00 or 5%, whichever is greater, of the original approved contract amount.  Change Order No. 05 is required due to unforeseen work not identified in the original contract award.  Community Services. (Commission District 3.) FOR POSSIBLE ACTION